Caijiaying Power and Safety Bureau Report

Griffin Mining Limited (“Griffin”) is pleased to report that the new 35kv mains power line has now been connected to the Caijiaying mine site and activated allowing work to commence on commissioning the new third main ball mill. Further to the announcement made on 19th October 2015, the Chinese state safety bureau have completed their […]


Caijiaying Operations

Griffin Mining Limited (“Griffin”) is pleased to report that further to the announcement made on 11th January 2016, the Chinese safety bureau has lifted its suspension order and allowed the recommencement of mining and haulage operations at Caijiaying. Blasting is expected to recommence by the end of the week.


Caijiaying Operations

Further to the announcement made on 14th January 2016, Griffin Mining Limited (“Griffin”) is pleased to confirm that approval to resume blasting has been given by all appropriate Chinese authorities and as such operations have fully recommenced at Caijiaying.


Directors Share dealings

This announcement replaces the release sent out on 16 February 2016 at 14.05 p.m. under RNS 2330P. Mr. Dal Brynelsen’s beneficial interest following the purchase should have been 412,001 shares, representing 0.2% of the Company’s issued share capital. The corrected version is set out below; all other details remain unchanged. Griffin Mining Limited (“Griffin”) has […]


Preliminary Results

Griffin Mining Limited (“Griffin” or the “Company”) has today published its preliminary results for the year ended 31st December 2015. Griffin and its subsidiaries (together the “Group”) recorded: Revenues of $59,779,000 in 2015 (2014 $45,564,000); Operating profit of $4,301,000 in 2015 (2014 $6,732,000); Loss before tax of $940,000 in 2015 (2014 Profit $1,021,000); and Loss […]


Annual Report and Accounts

The annual report and accounts of Griffin Mining Limited (“the Company”) for the year ended 31st December 2015, has been posted to shareholders and is available, on the Company’s web site www.griffinmining.com. The report and accounts can be downloaded from the Financials web page.


Appointment of General Manager at the Caijiaying Mine

Griffin Mining Ltd is pleased to announce the appointment of Mr Michael Hulmes as General Manager of the Caijiaying Mine. He has over 30 years experience in the mining industry having held senior management roles in Australia, Portugal, Papua New Guinea and Saudi Arabia including General Manager Lundin Mining in Portugal, General Manager Ok Tedi […]


Director Dealings

Mladen Ninkov has today notified Griffin Mining Limited (“the Company”) that on 6th May 2016, vested options over 4,000,000 shares in the Company together with unvested options over 8,000,000 shares in the Company, both exercisable at 30p per share, were sold for a consideration of £0.005 per option.


Annual General Meeting

Notice of the Annual General Meeting of Griffin Mining Ltd (“the Company”) to be held at 11.00 am (local time) on Thursday 14th July 2016 at Clarendon House, 2 Church Street, Hamilton, HM 11, Bermuda, has been sent to shareholders and is available on the Company’s web site www.griffinmining.com. The notice is available as a […]


Annual General Meeting

The Board of Griffin Mining Ltd (“the Company”) is pleased to announce that all the resolutions put to the shareholders of the Company at the Annual General Meeting held today were duly passed.